NTT DATA is reportedly in final talks to build Anthropic its first dedicated Japan data center in Osaka, at a cost of up to about $6.3 billion, the Nikkei reported.

NTT DATA is in the final stages of talks to build a data center in Osaka, western Japan, for Anthropic, the Nikkei reported, citing multiple sources, according to Reuters. It would be Anthropic's first dedicated facility in Japan.

Construction costs could reach up to 1 trillion yen, or about $6.3 billion, the report says. The data center would have a power intake capacity of up to 500 megawatts, with partial operations starting as early as 2028.

NTT DATA and Anthropic aim to sign an agreement by the end of fiscal 2026, which ends on March 31. NTT declined to comment.

We hope you enjoyed this article

Consider subscribing to one of our newsletters like Silicon Brief or Daily AI Brief.

Also, consider following us on social media:

Free newsletter

Silicon Brief

Weekly coverage of AI hardware developments including chips, GPUs, cloud platforms, and data center technology.

Whitepaper

Tensordyne Napier: What If One Rack Could Do the Work of Nine?

Tensordyne

This Tensordyne whitepaper presents Napier, an inference-focused AI processor and rack-scale system based on the company’s TDN Math logarithmic number system. It examines infrastructure requirements for large mixture-of-experts and agentic models, compares major inference architecture approaches, and details the TDN AIP processor, TDN72 pod, TDN Link fabric, and Napier Ultra configuration. The paper reports simulation-based performance, cost, and accuracy-validation results, including Tensordyne’s projected comparison of one Napier rack with a nine-rack Nvidia Rubin plus Groq deployment; the chip is reported as taped out and in fabrication.

Read more
Free, six days a week

Daily AI Brief: the AI news that matters, in your inbox.