Oracle Issues Force Majeure Notice for New Mexico Stargate Data Center
Oracle Corporation sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, according to TechCrunch. The notice could allow Oracle to delay payments if the facility misses its 2028 opening target, but the company is not seeking to exit as its main tenant.
Oracle said Project Jupiter remains on schedule. Blue Owl Capital, whose unit received the notice, said it does not change the financial commitments to the multiyear project.
The 2.45 gigawatt campus plans to use gas powered fuel cells from Bloom Energy. A pipeline intended to supply gas has been delayed until February 1, 2027, after permit denials, while an air quality permit for the fuel cell system remains pending.
We hope you enjoyed this article
Consider subscribing to one of our newsletters like Silicon Brief or Daily AI Brief.
Also, consider following us on social media:
More from Data Centers
Sep 25 Leopard Imaging and Lumotive Introduce Sirius Max 3D Perception Platform Sep 25 MetaOptics Establishes US ADR Program on OTCQX Sep 25 PrismML Brings Bonsai Model to Qualcomm Smart Glasses Platform Sep 24 Leviton Plans $100 Million Network Manufacturing Expansion Sep 24 Synteq Digital Opens Chicago GPU Infrastructure SiteSilicon Brief
Weekly coverage of AI hardware developments including chips, GPUs, cloud platforms, and data center technology.
Whitepaper
Tensordyne Napier: What If One Rack Could Do the Work of Nine?
Tensordyne
This Tensordyne whitepaper presents Napier, an inference-focused AI processor and rack-scale system based on the company’s TDN Math logarithmic number system. It examines infrastructure requirements for large mixture-of-experts and agentic models, compares major inference architecture approaches, and details the TDN AIP processor, TDN72 pod, TDN Link fabric, and Napier Ultra configuration. The paper reports simulation-based performance, cost, and accuracy-validation results, including Tensordyne’s projected comparison of one Napier rack with a nine-rack Nvidia Rubin plus Groq deployment; the chip is reported as taped out and in fabrication.
Read moreYou may also like
Island Roadhouse Plans 154 MW Atomic Powered AI Data Center in Missouri
MyOme Expands Genomic Risk Platform Worldwide on Oracle Cloud
Oracle and Buck Institute Use Health Data for Aging Research
Innventure removes DarkNX AI data centre cooling project from bookings
Galaxy Digital Receives ERCOT Classifications for 4.2 GW of Texas Data Center Capacity
Daily AI Brief: the AI news that matters, in your inbox.