UK AI data centres could emit 4.1 million tonnes of CO2 a year
Four planned hyperscale data centres in the UK are considering gas fired power while awaiting grid connections, according to BBC research. Together, they could require 1.3 gigawatts and emit an estimated 4.1 million tonnes of CO2 a year if they ran continuously at full capacity.
The UK Government set out a Data Centre Covenant in last Wednesday's Budget. The policy offers priority grid connections in exchange for local investment, jobs and water protections, while permitting developers to generate power on site where connections are unavailable.
Ofgem says data centre developers are seeking grid connections totalling 72 gigawatts, compared with peak UK electricity demand of 45 gigawatts last year. Some projects could wait up to 10 years for connections as the grid reaches capacity in many areas.
At Acre Slough, west of London, developers could use gas engines with up to 49.5 megawatts of capacity while awaiting a connection. Toby Perkins, chair of Parliament's Environmental Audit Committee, said a substantial increase in natural gas use should not be permitted.
We hope you enjoyed this article
Consider subscribing to one of our newsletters like Silicon Brief or Daily AI Brief.
Also, consider following us on social media:
More from Data Centers
Nov 5 Tenspresso Seeks $50 Million at $500 Million Valuation Nov 4 Arm second quarter revenue rises 27% to $1.44 billion Nov 4 Google Cloud Adds Security Controls for AI Agents Nov 4 Qualcomm Keeps $5 Billion Data Center Revenue Target for Fiscal 2027 Nov 4 Effingham County delays vote on OpenAI data center site planSilicon Brief
Weekly coverage of AI hardware developments including chips, GPUs, cloud platforms, and data center technology.
Industry analysis
2025 Global Business Services Agenda: Gen AI Takes Center Stage
This industry analysis by The Hackett Group explores the transformative impact of generative artificial intelligence (Gen AI) on global business services (GBS) in 2025. The study highlights the shift from exploration to acceleration of Gen AI initiatives, with 89% of executives advancing these projects to improve customer satisfaction, innovate products, and reduce costs. The report also discusses the challenges and strategies for successful Gen AI adoption, emphasizing the need for a technology-enabled operating model and the importance of reskilling the workforce.
Read moreYou may also like
Planned AI Data Centers Could Reverse 15 Years of US Emissions Cuts
National Grid Plans Britain’s Biggest Substation Near Teesside AI Data Centre
Drax and Brookfield plan AI data center worth over £20 billion
Germany Data Center Investment to Reach €23.5 Billion in 2026
Telehouse Completes £220 Million London Site Acquisition for 65 MW Data Center
Daily AI Brief: the AI news that matters, in your inbox.